Operations Manager- TRHDP

World Bank -- Tina River Hydropower Development Project · Solomon Islands government procurement

Bidding on World Bank-funded work in Solomon Islands? Get new Solomon Islands tenders by email, free: Set up alerts

Closed October 19, 2026. GlobalGov surfaces government procurement from around the world, including the markets your competitors overlook.

Closed
Status

Opportunity Overview

TERMS OF REFERENCE

CONSULTING SERVICES – INDIVIDUAL SELECTION

TERMS OF REFERENCE FOR INDIVIDUAL CONSULTANT

PART I:

Position

Operations Manager

Category of Consultancy

Local (Level 5)

Contract Type

Time-based Individual Consultant

Hiring Entity

TRHDP Project Office

Location

Honiara, Solomon Islands

Duration

2 years

Start date

As soon as possible upon agreement

Tina River Hydropower Development Project

Project Details

Strategic Context

The Tina River Hydropower Project is the first large-scale infrastructure to be developed under a public-private partnership arrangement and the first utility-scale renewable energy project for the Solomon Islands expected to deliver benefits such as more affordable electricity and improved accessibility to cleaner, more reliable energy sources for community now and in the future.

The Tina River Hydropower Project consists of (i) 15-megawatt hydropower facility located on the Tina River southeast of Honiara, comprising: a dam, headrace tunnel and a powerhouse about 3km downstream of the dam; (ii) access road to facilitate the construction and operation of the hydropower facility; and (iii) transmission lines - two parallel (on separate poles) single circuit transmission lines connecting the powerhouse to the existing Lungga Power Station. Further project details are included in Annex A.

The Tina Hydro Project Office under the Ministry of Mines, Energy and Rural Electrification is responsible for the coordination of the project activities to ensure Tina Hydropower Limited as implementing entity responsible for the hydropower facility and access road and Solomon Power as Offtaker under the Power Purchase Agreement fulfil their obligations under the project agreements. The Project Office has a fundamental advisory role to Solomon Islands Government, ensuring that the interests of the government are protected in line with the project agreements. The Project Office is responsible for monitoring and supporting the...

Your competitors are watching the same crowded contracts everyone else is. Track live opportunities like this one worldwide, set deadline alerts, and win where they aren’t. Free for 14 days, cancel anytime.

Start Free

Solicitation Details

Issuing agencyWorld Bank -- Tina River Hydropower Development Project
CountrySolomon Islands
CategoryHealth Services
PublishedOctober 01, 2026
Procurement stageSources Sought
ClosedOctober 19, 2026
StatusClosed — no longer accepting responses
Official sourceView original notice
Last verifiedOctober 21, 2026

Source: The World Bank — Open Data, licensed CC BY 4.0.

See every Solomon Islands Health Services opportunity your competition is missing. Free for 14 days.

Get real-time alerts, competitive intelligence, and deadline tracking for this and every market worldwide.

Start Your 14-Day Free Trial

Free 14-day trial · cancel anytime

See who is already competing here →

Get a free Solomon Islands Health Services intelligence report in your inbox

A personalized report on Solomon Islands Health Services opportunities, emailed in 5-10 minutes. One per month, no account needed.