Demolition, Removal, and Remediation

6913G6 VOLPE Natl Trans SYS CNTR · United States government procurement

Closed August 04, 2026. GlobalGov surfaces government procurement from around the world, including the markets your competitors overlook.

Closed
Status

Opportunity Overview

The Contractor shall submit a draft Demolition, Removal, and Restoration work plan (Work Plan) within 10 business days after attending a kickoff meeting with the Volpe Center representatives that addresses the project requirements below. This task involves the preparation and submission of a draft and final Work Plan. The Work Plan shall detail the technical approach and schedule for conducting all demolition, debris removal, disposal, and site restoration activities as required and described below. To assist with preparation of the Work Plan, the contractor shall thoroughly review the Government-furnished site survey report for the facility scheduled for demolition.

The Work Plan shall describe methods and procedures for dismantling, demolishing, and/or removing structures and equipment designated for disposal, and restoration of the site listed in Section 1.1. Site-specific information is detailed in Section 5.0 Proposed Scope of Work subsections B, C and D in the individual site survey report. The Work Plan shall also identify additional material sampling including sampling methods, analysis and quality control as may be required for waste characterization for all sites, if necessary. Disposal methods must be detailed for including the identification of all disposal facilities where waste and/or debris is to be shipped. In addition the work plan shall also identify any required permits needed to perform the work and the contractor shall be responsible for obtaining those permits as required. Copies of the permits shall be attached to the work plan as an appendix.

Additional components of the Work Plan are the Site Safety and Health Plan (SSHP), which shall include personnel health and safety precautions to be followed. The work plan shall also include a Risk Management Plan that identifies major risks and hazards on the site and discusses ways to minimize these risks. The contractor should expect a 5 business day Volpe Center review period between submission...

Your competitors are watching the same crowded contracts everyone else is. Track live opportunities like this one worldwide, set deadline alerts, and win where they aren’t. Free for 14 days, no card.

Start Free

Solicitation Details

Issuing agency6913G6 VOLPE Natl Trans SYS CNTR
CountryUnited States
CategoryEnvironmental Services
NAICS238910
PSCF999
PublishedJuly 23, 2026
Procurement stageRequest for Proposal (RFP)
ClosedAugust 04, 2026
StatusClosed — no longer accepting responses
Official sourceView original notice
Last verifiedAugust 12, 2026

Source: U.S. Government (SAM.gov) — public domain. GlobalGov is not affiliated with or endorsed by the United States Government.

Browse Similar Open Opportunities in United States

Worldwide Environmental Engineering Services
Integrated Solid Waste Management
DEPARTMENT OF ENERGY OFFICE OF ENVIRONMENTAL MANAGEMENT SPECIAL NOTICE - PROCUREMENT SCHEDULE UPDATE
U.S. Embassy Pretoria remediation works Family Housing complex
USMMA Vickery Gate Control Point (VGCP) Phase II
PPVG GEN V Award
State Border Security Reinforcement Fund
FY 2026 Continuum of Care Competition and Youth Homelessness Demonstration Program Grants NOFO

See every United States Environmental Services opportunity your competition is missing. Free for 14 days.

Get real-time alerts, competitive intelligence, and deadline tracking for this and every market worldwide.

Start Free Trial — No Card Required

Free 14-day trial · no card required

See who is already competing here →

Get a free United States Environmental Services intelligence report in your inbox

A personalized report on United States Environmental Services opportunities, emailed in 5-10 minutes. One per month, no account needed.