Why refurbishment is priced differently from new build
Refurbishment carries a risk new construction does not: nobody knows exactly what is behind the wall. Tender documents in this category are built around that uncertainty. Buyers commission condition and hazardous materials surveys before going to market and issue them with the bid pack, and bidders are normally required to attend a site visit that is a condition of admissibility rather than an option. A price submitted without the site visit is usually rejected, and a price submitted without reading the survey is usually regretted.
The pricing mechanism reflects the same uncertainty. Provisional sums and contingency allowances are written into the bill for work that can be foreseen but not quantified -- structural repair once finishes are stripped, asbestos removal, services that turn out not to match the record drawings. Those sums are expended against instruction and measured at agreed rates, so the rates a bidder offers for opening up and making good can matter more to the final account than the headline tender figure.
The constraint that most often drives cost is occupation. Much of this work happens in buildings that stay in use: schools during term, offices during business hours, wards that cannot close. That produces phased possession, temporary decant space, out-of-hours and weekend working, dust and noise limits, fire and escape route management around a live population, and separate security vetting for operatives. Heritage or listed status adds consents, specified materials and specialist trades on top. Bidders who price the work and not the phasing are the ones who claim for disruption later.
This section describes how this category is bought generally, across the public buyers that publish it. The figures elsewhere on this page are measured for this market alone.
Who buys renovation rehabilitation in Ukraine?
GlobalGov holds 69 renovation rehabilitation records from 60 distinct buying organisations in Ukraine. The most frequent publishers are Iom (2 records); Unicef (2 records); World Bank -- Health Enhancement And Lifesaving (heal) Ukraine Project (2 records); International buyer (2 records); International buyer (2 records); International buyer (2 records). Between them the 6 largest account for 17% of everything published, so buying here is spread across many separate authorities.
| Buying organisation | Records | Share |
|---|---|---|
| Iom | 2 | 2.9% |
| Unicef | 2 | 2.9% |
| World Bank -- Health Enhancement And Lifesaving (heal) Ukraine Project | 2 | 2.9% |
| International buyer | 2 | 2.9% |
| International buyer | 2 | 2.9% |
| International buyer | 2 | 2.9% |
What are renovation rehabilitation contracts worth in Ukraine?
60 of the 69 records publish a contract value. The median is $43,860 and the largest single published value is $1.0M. By size, 43 under $100k, 16 between $100k and $1M, 1 between $1M and $10M. The remaining 9 publish no value at all, so every figure here describes the priced subset only, and values are as stated by the buyer rather than as finally awarded.
| Contract size | Records | Share of priced |
|---|---|---|
| under $100k | 43 | 72% |
| between $100k and $1M | 16 | 27% |
| between $1M and $10M | 1 | 1.7% |
| above $10M | 0 | 0.0% |
How long do bidders get to respond to renovation rehabilitation tenders in Ukraine?
Across the 14 Ukraine renovation rehabilitation notices that publish both a publication date and a closing date, the median response window is 17 days. A quarter of them allowed 14 days or fewer and a quarter stayed open for more than 28. 3 of them (21%) closed within a fortnight of being published, so on this market a bidder who reviews notices once a week can lose most of the response window before reading one.
How often are renovation rehabilitation tenders published in Ukraine?
Ukraine publishes about 6 notices a month in this category, 68 in the last twelve months. Over the last three years there were 68, spread across 7 separate months of activity since 10 January 2022. April is historically the busiest month. No new notice has been published in this category since 4 June 2026, 119 days ago, so treat the figures above as a record of the market rather than as this week's pipeline.
How does Ukraine compare with other renovation rehabilitation markets?
Among the 44 countries where GlobalGov holds a comparable renovation rehabilitation market, Ukraine ranks 30th by number of records. The largest is Kenya (4,730 records against 69 here). Within Ukraine itself, renovation rehabilitation is the 12th largest of the 18 procurement categories tracked here.
Where do the Ukraine renovation rehabilitation records on this page come from?
These 69 records are collected from 4 official sources: Prozorro (59), UN Global Marketplace (4), the World Bank (4), TED (2). GlobalGov is an independent aggregator and is not affiliated with any of them; each record links back to the notice on its issuing portal. The set is rebuilt nightly, and the counts on this page were taken on 2026-10-01.
Most recent Renovation Rehabilitation tenders in Ukraine
None of these are open for bids now — they are the most recent records GlobalGov holds for this market, kept here so the shape of a typical renovation rehabilitation notice in Ukraine is visible. Set an alert to be told when the next one opens.
LRPS-2026-9203947 Rehabilitation works at 1 facility to create Child Rights Protection Center (CRPC) in Cherkasy
Request for Proposal (RFP) for the Renovation of the Administrative Building in Khotyn, Ukraine
Work performed at the site: "Renovation (restoration) to provide barrier-free access to services for people with special needs in the building of the 58th Officers' Club (Building No. 55/1), a monument of architecture and history (No. 5441-Lv) People’s House (the building where the West Ukrainian People’s Republic was proclaimed), Lviv, 22 Teatralna St.”
Preparation of cost estimate documentation, including an expert assessment, for the following project: “Renovation of part of the interior of the building of the Kharkiv City Council’s Municipal Children’s Polyclinic No. 16, located at 2 Louis Pasteur Street, Kharkiv”
Renovation of the club activity room at the Mashchanka Sports Club, part of the "Center for Cultural Services" Municipal Enterprise, Sumy Oblast, Okhtyrka District, village of Mashchanka, 9 Chotyrih Hann Street
Renovation (restoration) of an administrative building with an elevator shaft extension and installation of a vertical elevator and measures to improve accessibility
Other procurement categories in Ukraine
Renovation Rehabilitation procurement in other markets
Never Miss a Ukraine Government Contract
Finding Ukraine tenders usually means a local portal, a local registration and someone who reads the language. Get an alert you can read when a new renovation rehabilitation opportunity is published there.
Start Free Trial