Buying supply, generation and efficiency under one heading
Energy notices cover three different transactions that a bidder should separate before responding. The first is supply: a contract to deliver electricity or gas to meter points, priced as a unit rate with standing charges, awarded for a term and increasingly specified by generation source. The second is generation or connection assets -- plant, substations, heat networks, storage -- which is capital works with commissioning and grid connection at its centre. The third is performance-based efficiency work, which is a financing structure as much as a construction one.
Supply contracts turn on when the price is fixed. Buyers may take a fixed price for the whole term, fix in tranches as the market moves, or buy flexibly against a wholesale index with a supplier managing the purchasing, and the tender states which. Each puts the price risk in a different place, and comparing bids across mechanisms is not possible without modelling them on a common basis. Where renewable or low-carbon content is required, buyers now ask for certificate-backed evidence rather than a description of the supplier's generation mix.
Performance contracting deserves its own reading. In these arrangements the supplier designs and installs measures -- lighting, controls, heat generation, fabric -- and is paid from the savings, sometimes with a guarantee that underwrites them. The whole contract then rests on the measurement and verification protocol: the agreed baseline, the adjustments for weather and occupancy, and who measures. Bidders and buyers who negotiate the technology before the measurement protocol usually end up arguing about the measurement protocol.
This section describes how this category is bought generally, across the public buyers that publish it. The figures elsewhere on this page are measured for this market alone.
Who buys energy in Latvia?
GlobalGov holds 58 energy records from 44 distinct buying organisations in Latvia. The most frequent publishers are Balvu novada pašvaldība (4 records); Bauskas novada administrācija (3 records); Nodrošinājuma valsts aģentūra (3 records); Akciju Sabiedrība "augstsprieguma Tīkls" (2 records); Gulbenes Novada Pašvaldība (2 records); LR Tieslietu ministrijas Ieslodzījuma vietu pārvalde (2 records). Between them the 6 largest account for 28% of everything published, so buying here is spread across many separate authorities.
| Buying organisation | Records | Share |
|---|---|---|
| Balvu novada pašvaldība | 4 | 6.9% |
| Bauskas novada administrācija | 3 | 5.2% |
| Nodrošinājuma valsts aģentūra | 3 | 5.2% |
| Akciju Sabiedrība "augstsprieguma Tīkls" | 2 | 3.4% |
| Gulbenes Novada Pašvaldība | 2 | 3.4% |
| LR Tieslietu ministrijas Ieslodzījuma vietu pārvalde | 2 | 3.4% |
What are energy contracts worth in Latvia?
22 of the 58 records publish a contract value. The median is $1.0M and the largest single published value is $41.7M. By size, 11 between $100k and $1M, 9 between $1M and $10M, 2 above $10M. The remaining 36 publish no value at all, so every figure here describes the priced subset only, and values are as stated by the buyer rather than as finally awarded.
| Contract size | Records | Share of priced |
|---|---|---|
| under $100k | 0 | 0.0% |
| between $100k and $1M | 11 | 50% |
| between $1M and $10M | 9 | 41% |
| above $10M | 2 | 9.1% |
How long do bidders get to respond to energy tenders in Latvia?
Across the 15 Latvia energy notices that publish both a publication date and a closing date, the median response window is 35 days. A quarter of them allowed 30 days or fewer and a quarter stayed open for more than 39. Not one of them closed within a fortnight of being published, so the window on this market is consistently workable.
How often are energy tenders published in Latvia?
Latvia published 14 notices in this category in the last twelve months. Over the last three years there were 16, spread across 36 separate months of activity since 30 June 2016. June is historically the busiest month. The most recent was published 2 September 2026.
How does Latvia compare with other energy markets?
Among the 34 countries where GlobalGov holds a comparable energy market, Latvia ranks 30th by number of records. The largest is United States (2,062 records against 58 here). Within Latvia itself, energy is the 34th largest of the 47 procurement categories tracked here.
Where do the Latvia energy records on this page come from?
These 58 records are collected from 1 official source: TED (58). GlobalGov is an independent aggregator and is not affiliated with any of them; each record links back to the notice on its issuing portal. The set is rebuilt nightly, and the counts on this page were taken on 2026-10-01.
Open Energy tenders in Latvia
Showing 4 of the 5 notices open in this category today. Openness uses the same definition as the Latvia market page: active, not marked awarded, cancelled, closed or expired, and either closing in the future or published within the last 90 days with no stated closing date.
Latvia – Electricity – Elektroenerģijas piegāde Gulbenes novada pašvaldības vajadzībām
Latvia – Electricity – Dinamiskās iepirkumu sistēmas izveide centralizētas elektroenerģijas iegādes nodrošināšanai
Latvia – Electricity – Elektroenerģijas piegāde IeM padotībā esošajām iestādēm uz vienu gadu
Other procurement categories in Latvia
Energy procurement in other markets
Never Miss a Latvia Government Contract
Finding Latvia tenders usually means a local portal, a local registration and someone who reads the language. Get an alert you can read when a new energy opportunity is published there.
Start Free Trial