Power Transmission Government Tenders in Latvia

Who buys power transmission in Latvia, what it is worth, how long you get to bid, and what is open today. Counted 2026-10-01.

31
Records tracked
8
Buying organisations
0
Open right now
34 days
Median response window

Grid assets, outage windows and the compliance behind a connection

Transmission and distribution work is bought against a grid code rather than against a drawing. Equipment -- transformers, switchgear, conductors, protection and control systems -- must be type-tested to recognised standards and demonstrably compatible with the network it joins, and the compliance evidence is assessed before the commercial offer matters. Factory acceptance testing witnessed by the buyer, then site acceptance and energisation under the network operator's procedure, are defined stages with payment attached.

The scarcest resource in this category is not money or plant but the outage. Work on a live network happens in planned windows agreed months ahead with the system operator, frequently at night or in a season of low demand, and a window missed is not simply rescheduled. Contracts therefore concentrate risk and liquidated damages on the outage rather than on overall completion, and bidders are assessed on the credibility of their resourcing and logistics for those specific windows. Working near live conductors requires authorised personnel under a permit regime, and the authorisations are individual.

Lead times shape the programme more than construction does. Large transformers, high-voltage cable and switchgear are made to order with delivery measured in many months and a global order book competing for the same factory slots, so tenders commonly ask bidders to evidence a secured manufacturing slot rather than to state a delivery date. Land rights, wayleaves, environmental consent and public inquiry risk sit with the buyer on most schemes but govern when site work can start, and the contract's provisions for delayed access are worth reading before the programme is priced.

This section describes how this category is bought generally, across the public buyers that publish it. The figures elsewhere on this page are measured for this market alone.

Who buys power transmission in Latvia?

GlobalGov holds 31 power transmission records from 8 distinct buying organisations in Latvia. The most frequent publishers are AS "Sadales tīkls" (12 records); AS “Augstsprieguma tīkls” (10 records); Akciju sabiedrība "Augstsprieguma tīkls" (2 records); Akciju sabiedrība “Latvenergo” (2 records); Augšdaugavas novada pašvaldības Centrālā pārvalde (2 records); Rēzeknes novada pašvaldība (1 record). Between them the 6 largest account for 94% of everything published, so buying here is concentrated in a few authorities.

Buying organisationRecordsShare
AS "Sadales tīkls"1239%
AS “Augstsprieguma tīkls”1032%
Akciju sabiedrība "Augstsprieguma tīkls"26.5%
Akciju sabiedrība “Latvenergo”26.5%
Augšdaugavas novada pašvaldības Centrālā pārvalde26.5%
Rēzeknes novada pašvaldība13.2%

What are power transmission contracts worth in Latvia?

15 of the 31 records publish a contract value. The median is $1.6M and the largest single published value is $23.7M. By size, 5 between $100k and $1M, 9 between $1M and $10M, 1 above $10M. The remaining 16 publish no value at all, so every figure here describes the priced subset only, and values are as stated by the buyer rather than as finally awarded.

Contract sizeRecordsShare of priced
under $100k00.0%
between $100k and $1M533%
between $1M and $10M960%
above $10M16.7%

How long do bidders get to respond to power transmission tenders in Latvia?

Across the 15 Latvia power transmission notices that publish both a publication date and a closing date, the median response window is 34 days. A quarter of them allowed 30 days or fewer and a quarter stayed open for more than 39. Not one of them closed within a fortnight of being published, so the window on this market is consistently workable.

How often are power transmission tenders published in Latvia?

Latvia published 7 notices in this category in the last twelve months. Over the last three years there were 18, spread across 20 separate months of activity since 29 November 2021. February is historically the busiest month. No new notice has been published in this category since 4 March 2026, 211 days ago, so treat the figures above as a record of the market rather than as this week's pipeline.

How does Latvia compare with other power transmission markets?

Among the 26 countries where GlobalGov holds a comparable power transmission market, Latvia ranks 25th by number of records. The largest is Kenya (854 records against 31 here). Within Latvia itself, power transmission is the 44th largest of the 47 procurement categories tracked here.

Where do the Latvia power transmission records on this page come from?

These 31 records are collected from 1 official source: TED (31). GlobalGov is an independent aggregator and is not affiliated with any of them; each record links back to the notice on its issuing portal. The set is rebuilt nightly, and the counts on this page were taken on 2026-10-01.

Most recent Power Transmission tenders in Latvia

None of these are open for bids now — they are the most recent records GlobalGov holds for this market, kept here so the shape of a typical power transmission notice in Latvia is visible. Set an alert to be told when the next one opens.

Latvia – Construction work for electricity power lines – 330kV gaisvadu līniju balstu maiņa

Akciju sabiedrība "Augstsprieguma tīkls"$23.7MFebruary 24, 2026

Latvia – Construction work for electricity power lines – Ielu apgaismojuma inženiertīklu izbūve Augšdaugavas novadā

Augšdaugavas novada pašvaldības Centrālā pārvaldeValue not disclosedFebruary 09, 2026
All Latvia procurement →

Other procurement categories in Latvia

Medical EquipmentArchitecture and EngineeringCivil ConstructionVehicles and FleetRoads and Highways InfrastructureWaste ManagementSoftware DevelopmentOil Gas UpstreamVehicle MaintenanceFuel SupplyManagement ConsultingOffice FurnitureFood Aid and NutritionBuilding ConstructionLaboratory EquipmentFinancial AdvisoryAgricultural EquipmentScientific ResearchIct EquipmentUniforms ClothingGround TransportBuilding MaterialsPharmaceuticalsMilitary LogisticsTelecommunicationsFreight and LogisticsResearch & DevelopmentStaffing AugmentationIT ConsultingHospital ConstructionFacilities and CleaningMaintenance & RepairPrinting PublishingEnergyCommunications PrTraining and Capacity BuildingMail CourierWeapons SystemsSite PreparationTransportationCatering ServicesCommunity DevelopmentRenovation RehabilitationEvent ManagementDatabase ManagementResearch and Studies

Power Transmission procurement in other markets

KenyaFranceUnited StatesGermanyPolandSouth AfricaUgandaUkraineCroatiaSwitzerlandBulgariaIndia

Never Miss a Latvia Government Contract

Finding Latvia tenders usually means a local portal, a local registration and someone who reads the language. Get an alert you can read when a new power transmission opportunity is published there.

Start Free Trial