Transmission and distribution work is bought against a grid code rather than against a drawing. Equipment -- transformers, switchgear, conductors, protection and control systems -- must be type-tested to recognised standards and demonstrably compatible with the network it joins, and the compliance evidence is assessed before the commercial offer matters. Factory acceptance testing witnessed by the buyer, then site acceptance and energisation under the network operator's procedure, are defined stages with payment attached.
The scarcest resource in this category is not money or plant but the outage. Work on a live network happens in planned windows agreed months ahead with the system operator, frequently at night or in a season of low demand, and a window missed is not simply rescheduled. Contracts therefore concentrate risk and liquidated damages on the outage rather than on overall completion, and bidders are assessed on the credibility of their resourcing and logistics for those specific windows. Working near live conductors requires authorised personnel under a permit regime, and the authorisations are individual.
Lead times shape the program more than construction does. Large transformers, high-voltage cable and switchgear are made to order with delivery measured in many months and a global order book competing for the same factory slots, so tenders commonly ask bidders to evidence a secured manufacturing slot rather than to state a delivery date. Land rights, wayleaves, environmental consent and public inquiry risk sit with the buyer on most schemes but govern when site work can start, and the contract's provisions for delayed access are worth reading before the program is priced.
This section describes how this category is bought generally, across the public buyers that publish it. The figures elsewhere on this page are measured for this market alone.
Who buys power transmission in Romania?
GlobalGov holds 77 power transmission records from 57 distinct buying organizations in Romania. The most frequent publishers are Distribuție Energie Electrică Romania S.a. (8 records); SPEEH Hidroelectrica SA (4 records); Delgaz Grid S.A. (3 records); Universitatea Maritima Din Constanta (3 records); Compania Nationala Aeroporturi Bucuresti SA (2 records); Metrorex S.A. (2 records). Between them the 6 largest account for 29% of everything published, so buying here is spread across many separate authorities.
| Buying organization | Records | Share |
|---|---|---|
| Distribuție Energie Electrică Romania S.a. | 8 | 10% |
| SPEEH Hidroelectrica SA | 4 | 5.2% |
| Delgaz Grid S.A. | 3 | 3.9% |
| Universitatea Maritima Din Constanta | 3 | 3.9% |
| Compania Nationala Aeroporturi Bucuresti SA | 2 | 2.6% |
| Metrorex S.A. | 2 | 2.6% |
What are power transmission contracts worth in Romania?
60 of the 77 records publish a contract value. The median is $1.1M and the largest single published value is $829.4M. By size, 6 under $100k, 23 between $100k and $1M, 17 between $1M and $10M, 14 above $10M. The remaining 17 publish no value at all, so every figure here describes the priced subset only, and values are as stated by the buyer rather than as finally awarded.
| Contract size | Records | Share of priced |
|---|---|---|
| under $100k | 6 | 10% |
| between $100k and $1M | 23 | 38% |
| between $1M and $10M | 17 | 28% |
| above $10M | 14 | 23% |
How long do bidders get to respond to power transmission tenders in Romania?
Across the 41 Romania power transmission notices that publish both a publication date and a closing date, the median response window is 36 days. A quarter of them allowed 34 days or fewer and a quarter stayed open for more than 38. Short turnarounds are the exception rather than the rule here: only 3 (7.3%) closed within a fortnight of being published.
How often are power transmission tenders published in Romania?
Romania published 16 notices in this category in the last twelve months. Volume is steady against the 17 published in the twelve months before that. Over the last three years there were 40, spread across 37 separate months of activity since 23 May 2014. March is historically the busiest month. No new notice has been published in this category since 1 April 2026, 235 days ago, so treat the figures above as a record of the market rather than as this week's pipeline.
How does Romania compare with other power transmission markets?
Among the 32 countries where GlobalGov holds a comparable power transmission market, Romania ranks 15th by number of records. The largest is Kenya (854 records against 77 here). Within Romania itself, power transmission is the 52nd largest of the 68 procurement categories tracked here.
Where do the Romania power transmission records on this page come from?
These 77 records are collected from 2 official sources: TED (64), the Romania national tender archive (13). GlobalGov is an independent aggregator and is not affiliated with any of them; each record links back to the notice on its issuing portal. The set is rebuilt nightly, and the counts on this page were taken on 2026-11-22.
Most recent Power Transmission tenders in Romania
None of these are open for bids now — they are the most recent records GlobalGov holds for this market, kept here so the shape of a typical power transmission notice in Romania is visible. Set an alert to be told when the next one opens.
Romania – Electricity – Acord-Cadru Furnizare Energie Electrica
“Construction of an approximately 850 MW natural gas-fired power plant in Ișalnița (“CCGT Ișalnița”)” – design, procurement, construction, commissioning, and long-term maintenance services
Romania – Electricity distribution and control apparatus – Achiziție utilaje/echipamente/dotări care nu necesită montaj, inclusiv active necorporale în cadrul Proiectului: Îmbunătățirea Infrastructurii Educaționale Universitare la Centrul Universitar UBB Reșița- prioritatea 2, Cod Smis 2021: 331225
Romania – Generator units – CONTRACT DE ACHIZITIONARE GRUP GENERATOR (715 KVA) - 3 buc
Romania – Electricity distribution and control apparatus – IMPEDANTE SI DISPOZITIVE DE PROTECTIE _ RETELE ELECTRICE ROMANIA S.A.
Romania-București: Installation services of electricity distribution equipment
Other procurement categories in Romania