Impact assessment, its statutory timetable and who is allowed to write it
An environmental impact assessment is a statutory process with a prescribed sequence, and the procurement has to fit inside it. Screening establishes whether a formal assessment is required at all; scoping settles which effects will be examined and to what depth, usually in consultation with the regulator; the assessment itself gathers baseline data and predicts effects; and the resulting statement is published and consulted on. Each stage has a consultation period nobody can compress, so a bid whose programme omits them is not credible.
Baseline surveys are the immovable constraint. Ecological, noise, air quality and hydrological baselines can only be gathered in particular seasons or over particular durations, and a survey done outside its valid window will be challenged. Competent expert requirements apply: many jurisdictions require the assessment to be prepared by suitably qualified people and to say who they were, so the bid names specialists per topic rather than offering a firm.
The commercial risk sits after submission. Regulator and consultee requests for further information, and in contested cases a public inquiry or hearing, extend the work well beyond the statement, and expert witness attendance is a separate and expensive commitment. Tenders should be read for whether that is included, capped or excluded. Independence matters too: an assessment written by a consultant with an interest in the project proceeding is vulnerable to challenge on exactly that ground, which is why conflict declarations in this category cover the wider group and not only the team.
This section describes how this category is bought generally, across the public buyers that publish it. The figures elsewhere on this page are measured for this market alone.
Who buys environmental assessment in Poland?
GlobalGov holds 37 environmental assessment records from 25 distinct buying organisations in Poland. The most frequent publishers are Regionalna Dyrekcja Ochrony Środowiska w Poznaniu (5 records); Regionalna Dyrekcja Ochrony Środowiska w Gdańsku (4 records); Narwiański Park Narodowy (3 records); Gmina Nowogard (2 records); Regionalna Dyrekcja Ochrony ŚRodowiska W Białymstoku (2 records); Regionalna Dyrekcja Ochrony Środowiska w Lublinie (2 records). Between them the 6 largest account for 49% of everything published, so buying here is spread across many separate authorities.
| Buying organisation | Records | Share |
|---|---|---|
| Regionalna Dyrekcja Ochrony Środowiska w Poznaniu | 5 | 14% |
| Regionalna Dyrekcja Ochrony Środowiska w Gdańsku | 4 | 11% |
| Narwiański Park Narodowy | 3 | 8.1% |
| Gmina Nowogard | 2 | 5.4% |
| Regionalna Dyrekcja Ochrony ŚRodowiska W Białymstoku | 2 | 5.4% |
| Regionalna Dyrekcja Ochrony Środowiska w Lublinie | 2 | 5.4% |
What are environmental assessment contracts worth in Poland?
7 of the 37 records publish a contract value. The median is $935,158 and the largest single published value is $3.6M. By size, 2 under $100k, 3 between $100k and $1M, 2 between $1M and $10M. The remaining 30 publish no value at all, so every figure here describes the priced subset only, and values are as stated by the buyer rather than as finally awarded.
| Contract size | Records | Share of priced |
|---|---|---|
| under $100k | 2 | 29% |
| between $100k and $1M | 3 | 43% |
| between $1M and $10M | 2 | 29% |
| above $10M | 0 | 0.0% |
How long do bidders get to respond to environmental assessment tenders in Poland?
Across the 30 Poland environmental assessment notices that publish both a publication date and a closing date, the median response window is 34 days. A quarter of them allowed 32 days or fewer and a quarter stayed open for more than 36. Short turnarounds are the exception rather than the rule here: only 2 (6.7%) closed within a fortnight of being published.
How often are environmental assessment tenders published in Poland?
Poland publishes about 2 notices a month in this category, 26 in the last twelve months. Over the last three years there were 31, spread across 6 separate months of activity since 13 May 2025. February is historically the busiest month. No new notice has been published in this category since 13 April 2026, 171 days ago, so treat the figures above as a record of the market rather than as this week's pipeline.
How does Poland compare with other environmental assessment markets?
Among the 9 countries where GlobalGov holds a comparable environmental assessment market, Poland ranks 7th by number of records. The largest is United States (1,115 records against 37 here). Within Poland itself, environmental assessment is the 68th largest of the 73 procurement categories tracked here.
Where do the Poland environmental assessment records on this page come from?
These 37 records are collected from 2 official sources: TED (26), e-Zamowienia (11). GlobalGov is an independent aggregator and is not affiliated with any of them; each record links back to the notice on its issuing portal. The set is rebuilt nightly, and the counts on this page were taken on 2026-10-01.
Most recent Environmental Assessment tenders in Poland
None of these are open for bids now — they are the most recent records GlobalGov holds for this market, kept here so the shape of a typical environmental assessment notice in Poland is visible. Set an alert to be told when the next one opens.
Poland – Environmental services – Aktualizacja operatu GIS
Poland – Environmental services – Aktualizacja planu ochrony dla Bieszczadzkiego Parku Narodowego z uwzględnieniem przedmiotów ochrony Natura 2000 PLC 180001 Bieszczady w granicach Parku
Polska – Usługi doradcze w zakresie środowiska naturalnego – Ekspertyzy fitosocjologiczne i botaniczne na potrzeby projektu PZO3 – część 6
Other procurement categories in Poland
Environmental Assessment procurement in other markets
Never Miss a Poland Government Contract
Finding Poland tenders usually means a local portal, a local registration and someone who reads the language. Get an alert you can read when a new environmental assessment opportunity is published there.